Summary
This is a machine-generated summary.
(1) The National Power Grid Corporation of China's Inner Mongolia Shanghai Miao Energy Company submitted an Environmental Impact Report for the 4x1000MW Power Generation Project at the Inner Mongolia Shanghai Miao Power Plant, specifically for the 500kV Substation Construction Project. After reviewing the report, the Inner Mongolia Autonomous Region Environmental Protection Bureau has made the following decision:
(2) The project has been completed and put into operation since August 2021, and the Inner Mongolia Autonomous Region Environmental Protection Bureau has issued a decision not to impose administrative penalties on the project (Inner Mongolia Autonomous Region Environmental Protection Bureau [2025] No. 5). Based on the original Environmental Protection Bureau's Opinion on the Application of Legal Rules to the Unapproved Construction (Environmental Protection Bureau [2018] No. 31), from an environmental and policy perspective, the project meets the requirements of the relevant documents, and the Bureau agrees in principle to the environmental impact assessment approval of the project.
(3) During the project's operation period, the following work should be done:
(4) (1) Strictly implement the ecological environmental protection measures during the operation period, and do a good job in the ecological protection of the surrounding areas.
(5) (2) Seriously implement the measures and methods proposed in the report for controlling and improving the impact of the project on the surrounding environment in terms of frequency field and frequency magnetic field, and the monitoring values should meet the requirements of the Electromagnetic Environment Control Limits (GB8702-2014).
(6) (3) During the operation period, the substation's living wastewater should be treated by the existing underground integrated wastewater treatment facilities within the plant. All waste transformer oil and waste batteries generated during equipment maintenance should be recycled. If they cannot be recycled entirely, they should be stored separately and sent to units with the corresponding hazardous waste business qualifications for disposal.
(7) (4) The noise values and noise prevention measures during the operation period should meet the requirements proposed in the report, and the monitoring values should meet the national evaluation standard limits.
(8) The construction unit should complete the post-construction environmental protection acceptance in accordance with the prescribed procedures by March 12, 2025.